Runway 4-22 extension project

Texarkana

Summary

The council approved a bundle of airport items covering the Runway 4-22 extension and overlay: a $15.79 million construction contract with Tatum Excavating, engineering administration agreements, and securing up to $20.8 million in federal funding. It's largely grant-funded and keeps the regional airport growing.

At a glance

Total mentions
1
Last 30 days
0

Last discussed May 11, 2026.

Impact analysis

💰Financial impact

The $15.79 million construction contract is funded mainly by federal and Arkansas grants plus budgeted city matching funds.

✅Who benefits

Travelers and businesses using the Texarkana Regional Airport.